Project Title: 
Clyde River Substation, Clyde River, PEI., detailed design and site development
Services We Provided: 
- Electrical Engineering Studies
- Design and Specifications
- Field Services
- Project Management
Project Description

Project involved the design of a new 138kV-25kV, 20MVASubstation at Clyde River, PEI.

Scope of Work

The specific scope of the project included the following elements:

  • Preparation of general arrangement drawings, and overall site plan for the substation.
  • Preparation of civil earthworks design including design drawings and specifications (Sub-consultant Brian Latimer, P.Eng.) 
  • Preparation of design drawings and specifications for the galvanized steel structures and the associated concrete bases for 138kV and 25kV equipment
  • Design of substation fence. 
  • Design of concrete cable trench, cable tray and conduit system between the control building and the substation equipment. 
  • Design of all bulk power system interconnections.